| Checking of Emergency Lighting -
Goodwood Court |
Checking of Emergency Lighting - Eaton Centre |
| 17/05/2009 One hour test completed - bulbs replaced in
rooms 3 and 8. All satisfactory |
22/9/2009 one hour fire test successful except in waiting
room. New luminaires to be installed |
| 19/9/2009 On hour test completed - all satisfactory
apart from luminaire over entrance door - to be replaced |
14/01/2010 Emergency lights re-fitted and fully tested |
| 23/9/2009 Luminaire replaced |
31/1/2010 Emergency lights tested. Central light in Reception office
failed. Identified that no emergency light in Patient toilet.
Electricians contacted (1/2/2010) to obtain replacements and to fit new
light in toilet |
| 14/01/2010 3 hour emergency lighting test completed |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|